Marine engineering services team providing aftermarket support for U.S. Navy equipment

Pit Stop Program

At Fairbanks Morse Defense, we’ve reimagined naval maintenance by drawing inspiration from an unlikely source—NASCAR. Just as a pit crew services a car in seconds with precision and preparation, our Pit Stop Program transforms traditional ship maintenance into a proactive, streamlined process that minimizes downtime and maximizes fleet readiness.

WHAT IS THE PIT STOP PROGRAM?

The Pit Stop Program is a proactive, standardized maintenance approach designed to replace the unpredictable “open and inspect” method. By leveraging advanced planning, pre-staged overhaul kits, and a closed-loop part refurbishment system, we deliver faster, more reliable maintenance solutions.

  • Dramatically Shortened Timelines: Maintenance periods are reduced from months to weeks.
  • Significant Cost Reductions: Standardized parts and controlled refurbishments lower costs without compromising quality.
  • Improved Fleet Availability: More ships are mission-ready, enhancing naval power and operational flexibility.

Key Features of the Pit Stop Program

  • Advanced Planning: Maintenance is pre-planned with a predictable scope of work, eliminating delays caused by unexpected discoveries.
  • Pre-Staged Overhaul Kits: Complete engine component sets are refurbished, kitted, and shipped to vessels ahead of maintenance windows.
  • Closed-Loop Refurbishment: Removed components are overhauled and replenished for future use, ensuring a sustainable inventory.
  • Standardized Processes: Detailed project plans and OEM-validated procedures ensure consistent, repeatable outcomes

Minimizing Downtime, Maximizing Readiness

The Pit Stop Program has already delivered remarkable results for Whidbey Island-Class LSDs:

  • Reduced overhaul timelines from 9 months to under 2 months.
  • Achieved a 60% faster maintenance turnaround compared to traditional methods.
  • Improved fleet availability and reduced costs.

Examples of Success:

  • USS ASHLAND: Overhauled 3 SSDGs in under 26 days each.
  • USS GUNSTON HALL: Completed 1 MPDE overhaul in under 38 days, including warranty work.
  • USS PEARL HARBOR: Overhauled 1 SSDG in under 26 days.
  • USS OAK HILL: Overhauled 2 MPDEs in just 52 days combined.